|
|
|
|
|
|
|
CATCO
Maintaining Uptime, Times Two…Make That Times Three!
Concrete Applied Technology Corporation.
Buffalo, New York
|
For a large construction company such as Buffalo New York’s Concrete Applied Technology Corporation, or CATCO, widening a road to accommodate a mandated center turning lane, and in preparation for an expected 3% annual increase in traffic volume, is a project that falls well within the range of “business as usual.” But in the case of a 2,600 meter section of Buffalo’s Niagara Falls Boulevard, there were a couple of additional challenges thrown in with the job. One was the fact that for the widening to take place, 1,500 meters of a creek needed to be relocated, and life needed to go on for the businesses and people living on both sides of the road and creek during the relocation. Another added challenge was the environmental concerns involved in relocating the wildlife that inhabited Sawyer Creek. And, as if all the rest was not enough, the weather didn’t cooperate.
“We actually checked the records,” says Mike Nassoiy, CATCO’s supervisor on the job, “and we saw that the last time it had rained that much during the period between Labor Day and October had been 100 years ago!” Needless to say, rainy conditions threw a big wrench into the job. The water levels were 8 to 9 feet higher than normal and the soil turned too soft to work. The window of opportunity was getting pretty tight as certain stages of the project needed to be completed by the end of December to keep the job on schedule.
|
|
The first step in creating a new creek bed was to line the bottom with the base sediment from the existing bed to allow for better, faster growth of vegetation and a better environment for the wildlife.
|
|
|
|
Protecting Sawyer Creek’s wildlife, and preserving and improving their habitat was a very real parameter for CATCO in the planning and execution of the creek relocation. |
|
“The Army Core of Engineers was very clear on the need to relocate the creek using a very specific process and to very specific parameters,” tells Nassoiy, and he continues, “The terms on the permit spelled out that the wildlife in the creek was to be carefully removed, and in addition, we were asked to move two feet of sediment at the bottom of the ‘old’ creek and use it to line the bed of the newly dug one so that the vegetation could take root and the fish and turtles would feel at home.” When Nassoiy is asked about some of the details about the wildlife removal process, he shakes his head. “The fish were easy,” he says, “we used nets to catch them and then we’d release them in the newly excavated, lined and flooded sections; what was more challenging frankly were the turtles!” Apparently the CATCO crew members were a bit intimidated by snapping turtles that were three feet and larger and had to rely on their expertise operating the CAT wheel loaders to load the turtles into the bucket and gently but safely transport the creatures to their new home and release them.
|
|
Before any machinery hit the ground a lot of hard work had already been done, planning the strategy for the job and making sure all the pieces were in place. “The contract was awarded February 6th of 2006, and by end of March we broke dirt,” says Nassoiy, “and what followed was pretty intense!”
According to Nassoiy the job was divided into three phases – the building of driveway structures (23 of them in total), creek relocation and the paving of the new lane – each of which involved many different steps and required the crews to push themselves, and their CAT equipment, achieving ambitious schedules. “We knew if we needed anything as far as parts or a different worktool, whatever it was, the Milton CAT guys understood how tight things were and they never let us down,” says CATCO founder and owner Mike Salvadore.
|
 |
| Within a span of 8 months, Sawyer Creek and its accompanying Buffalo’s Niagara Falls Boulevard were transformed with as little interruption as possible to all inhabitants – both wildlife and human. |
|
|
|
During the building of the 23 new driveway structures in Phase One, the creek needed to be bulkheaded at certain points and the creek water pumped around the construction areas and back into the creek downstream. |
|
The project was comprised of the following phases:
Phase One – June to September
The building of new driveway structures over the future creek location so businesses and homeowners would never lose access to Buffalo’s Niagara Falls Boulevard while creek was being relocated.
Steps included:
1) Build new driveway structures, including culverts, footers, beams and end walls.
2) Backfill and “jog” creek at each new driveway location.
3) Open new driveway structures one at a time.
4) Remove the old structures.
According to Nassoiy steps 1-4 took four weeks, and the process was repeated 23 times.
|
|
Phase Two – September to December
The relocation of the creek was done in 800 ft sections, each section taking 3-4 days.
Steps included:
1) Dig new creek bed between each new driveway structure. 2) Line new bed with two feet of sediment that had been removed from the bed of existing creek.
3) Fill old creek bed to build base for the 5th highway lane to be added. Six feet of stone and crushed remains of old driveway structures were used to accomplish this task.
4) Open up the bulkhead dam to release the water into the new bed with the help of gravity.
Phase three is the final preparation and paving of the added lane after all utility poles have been moved and the service lines have been transferred.
|
 |
| The placement of the new utility poles where the creek used to be, gives a good indication as to the ground gained in relocating the creek. |
|
|
|
The relocation of Sawyer Creek served to not only allow an increase in the width of the roadway, but a restoration of the creek itself. |
|
Throughout all the intense months of work, made up of 16 hours days and compounded by the most challenging circumstances that a project could have and that mother nature could add, the CATCO project crew, their equipment and their support teams finished their work on time and to the satisfaction of all concerned.
According to New York State Department of Transportation Engineer and Project Manager Tom Skummer, P.E., “I will never forget the times that the excavator operators would come across turtles that had burrowed themselves into the creek mud, and how the operators, with a light touch, would pick the turtle up with the excavator bucket and place him on the bank.” He continues, “CATCO relocated the creek in an efficient and timely manner, keeping a wary eye on the weather and the problems that it brought to the project, as well being cognizant of the environmental guideline established by all the government agencies involved. They did a great job!”.
|
|
|
|
|
|
|
|
|
|